A majority of the backfill and engineered fill is complete. Base rock will be placed within a week followed by the installation of reinforcing steel. The concrete floor slab is scheduled to pour on July 25th. Following the completion of the concrete slab, layout for the glulam column base plates and interior wall plates will occur. This photo is also from July 2.
A majority of the backfill and engineered fill is complete. Base rock will be placed within a week followed by the installation of reinforcing steel. The concrete floor slab is scheduled to pour on July 25th. Following the completion of the concrete slab, layout for the glulam column base plates and interior wall plates will occur. This photo is also from July 2.