Live Oak Updates 5.5.2021

Construction documents have been completed and the RFP should be approved by the County in May. The branch will likely close for a few months in the autumn of 2021. The remodel should be complete in 2021. Live Oak Annex Construction documents and permitting are concluding. The County will advertise and bid the project th ...Read More

Updated: 05/05/2021
Branch: Live Oak
See all updates for
Live Oak

 

La Selva Beach Updates 5.5.2021

A virtual grand opening event was held on March 20 with over 100 attendees. A recorded version is available at https://www.youtube.com/watch?v=7Eg6TP8z8l0. A virtual tour and a 3D tour are available on the Library website as well. The Community has begun to use the branch for Grab and Go services, three days a week and now ...Read More

Updated: 05/05/2021
Branch: La Selva Beach
See all updates for
La Selva Beach

 

Garfield Park Updates 5.5.2021

The City approved CRW Industries of Scotts Valley as the construction contractor. The Library has emptied the facility and construction has begun. The remodeled library should open in late 2021. ...Read More

Updated: 05/05/2021
Branch: Garfield Park
See all updates for
Garfield Park

 

Felton Branch Updates 5.5.2021

County staff continues to finalize closeout documents but will still need to resolve some stormwater and traffic mitigation issues. ...Read More

Updated: 05/05/2021
Branch: Felton
See all updates for
Felton

 

Capitola Update 5.5.2021

Capitola Capitola is on track for a June 12 Grand Opening. Furniture is being delivered and the contractor’s punch list is being completed. Books are arriving and being shelved. The Library is expected to have occupancy around May 1. The grand opening is being planned. ...Read More

Updated: 05/05/2021
Branch: Capitola
See all updates for
Capitola

 

Page 4 of 24

Updates: All

Live Oak Updates 5.5.2021

Construction documents have been completed and the RFP should be approved by the County in May. The branch will likely close for a few months in the autumn of 2021. The remodel should be complete in 2021. Live Oak Annex Construction documents and permitting are concluding. The County will advertise and bid the project th ...Read More

Updated: 05/05/2021
Branch: Live Oak
See all updates for
Live Oak

 

La Selva Beach Updates 5.5.2021

A virtual grand opening event was held on March 20 with over 100 attendees. A recorded version is available at https://www.youtube.com/watch?v=7Eg6TP8z8l0. A virtual tour and a 3D tour are available on the Library website as well. The Community has begun to use the branch for Grab and Go services, three days a week and now ...Read More

Updated: 05/05/2021
Branch: La Selva Beach
See all updates for
La Selva Beach

 

Garfield Park Updates 5.5.2021

The City approved CRW Industries of Scotts Valley as the construction contractor. The Library has emptied the facility and construction has begun. The remodeled library should open in late 2021. ...Read More

Updated: 05/05/2021
Branch: Garfield Park
See all updates for
Garfield Park

 

Felton Branch Updates 5.5.2021

County staff continues to finalize closeout documents but will still need to resolve some stormwater and traffic mitigation issues. ...Read More

Updated: 05/05/2021
Branch: Felton
See all updates for
Felton

 

Capitola Update 5.5.2021

Capitola Capitola is on track for a June 12 Grand Opening. Furniture is being delivered and the contractor’s punch list is being completed. Books are arriving and being shelved. The Library is expected to have occupancy around May 1. The grand opening is being planned. ...Read More